53 percent of Birmingham's treated water never reaches a customer. Half the product, lost to aging infrastructure.
Somewhere beneath Birmingham, Alabama, half of the treated water never reaches a customer. It leaks from cracked pipes, failed joints, and aging infrastructure that has been deteriorating for decades.
The number is 53 percent. According to Bluefield Research and ABC 33/40 reporting, more than half of all treated water produced by Alabama's largest water utility in 2024 was never billed to anyone[1][11]. Roughly 40 percent of that total is physical loss — water leaking from pipes into the ground before it ever reaches a customer[2].
There is no mystery here and no sign of sabotage. Half the product is lost through a combination of deferred maintenance, failed technology upgrades, and governance failures that compounded over decades.
The utility responsible was called the Birmingham Water Works Board until 2026, when it was reorganized into Central Alabama Water. The name changed but the pipes did not. There are 584 miles of old pipe remaining in the system, some of them over a hundred years old, and at the current replacement rate it would take forty years to replace them all[3][10].
Utilities do not reach 53 percent non-revenue water overnight. The problem accumulates slowly enough that each budget cycle defers it, and steadily enough that the eventual cost far exceeds what planned maintenance would have required.
What the AVEVA Presentation Revealed
In 2022, at the AVEVA World conference in San Francisco, a presentation was given about the Birmingham Water Works Board. The presenter was Dean Ford, a managing principal engineer at Luminary Automation, Cybersecurity and Engineering, the firm helping the utility modernize its control systems[1].
The presentation made a rare public admission: several homegrown and consultant-written proprietary applications were running the utility's SCADA supervisory control system on platforms like Windows 2000 and Windows 2003. Microsoft ended support for both of those operating systems over a decade ago. The SCADA HMI layer — the interface that operators use to monitor and control water treatment, pumping, and distribution — was running on Foxboro I/A Series systems with decades-old software. The plan was to replace the HMI portion with AVEVA System Platform, AVEVA Historian, and AVEVA Reports for Operations[1].
The presentation framed this as the first step in a multiyear journey toward OT-IT-ET convergence, meaning operational technology, information technology, and enterprise technology all working together. It was the right direction. The problem was that by 2022, the utility was already fifteen years behind.
The Systems That Should Have Prevented This
A modern water utility needs three things to manage its distribution network: automated meter infrastructure to detect leaks in real time, a functioning customer information system to track billing and revenue, and SCADA sensors across the network to monitor pressure, flow, and water quality.
The Birmingham Water Works Board had none of these in adequate measure.
The automated meter reading system — the single most important technology for reducing non-revenue water — was delayed due to budget constraints. Reporting in October 2025 confirmed that the utility was reconsidering and slowing AMI deployment along with pipeline replacement and dam-related work[3]. The new target for full deployment is 2028. Even if that date holds, instrumenting 584 miles of distribution network will take years.
Separately, the customer information system running on SAP tracks water meters, billing, maintenance work orders, and asset tracking. In late 2025, the utility announced that the entire SAP system must be replaced before 2027 or it fails. A vendor bidding process was expected to conclude in late 2025, with full deployment targeted for 2028[3][8].
Without a functional SAP system, the utility cannot accurately track which meters are working, which customers are being billed, or where maintenance crews need to be sent. Without AMI, the utility cannot detect leaks before they surface as water main breaks. Without modern SCADA sensors across the distribution network, pressure anomalies and flow discrepancies go unnoticed until a pipe fails. The utility is managing a network it fundamentally does not understand.
The Money Problem
Non-revenue water is, at its core, a revenue problem. The utility treats water it never bills for, paying for electricity, chemicals, treatment labor, and pumping capacity, and gets zero income from roughly half of it. That revenue gap forces capital budget cuts, and the October 2025 budget cuts directly delayed the very technologies that would reduce non-revenue water[3].
The cycle works like this: high non-revenue water means low revenue, low revenue means capital cuts, and capital cuts mean automated meters get deferred while pipe replacement slows. Deferred meters and slow replacement mean non-revenue water stays high or climbs higher, which means lower revenue and more cuts.
Breaking this cycle requires external funding through federal grants, state assistance, or bond issuance. Rate increases are politically toxic for a utility already under state audit scrutiny. Bond issuance requires demonstrating fiscal responsibility, which the state audit explicitly undermined[5][6]. Federal grants through the Bipartisan Infrastructure Law require matching funds and demonstrated project readiness, both of which are weak.
The capital cost to reduce non-revenue water from 53 percent to even 25 percent — still well above the AWWA industry standard of 10 to 15 percent — is in the hundreds of millions of dollars. The utility's annual operating budget cannot support it, and there is no credible funding path to get there.
The Governance Failure
In December 2025, an Alabama state audit covering May 2023 through May 2025 found that the former Birmingham Water Works Board was failing at basic governance[5][6].
The audit found that a former general manager received approximately $245,735 in accrued sick leave that auditors said was not allowed by board policy. The board did not comply with Alabama's Competitive Bid Law in the way it documented and awarded contracts. Some board members were paid for meetings they did not attend. The board lacked written purchasing-card policies and had ineffective internal controls. It lacked formal inventory and equipment tracking policies, which auditors linked to documented equipment losses[5].
This audit covered the exact period when SCADA modernization, SAP replacement, automated meter deployment, and pipeline replacement were all supposed to be advancing.
When a utility violates bid law, it loses vendor trust and pays more for less. When it lacks inventory tracking, equipment disappears. When board members are paid for meetings they do not attend, the people who should be making capital decisions are not there to make them. Good governance is the foundation of capital allocation. Without it, every dollar is at risk.
The 2026 Reorganization
In 2026, the Birmingham Water Works Board was reorganized into Central Alabama Water. New name, new board, new structure. The political accountability was reset.
The infrastructure deficit remains exactly what it was before the vote: 584 miles of aging pipe, SCADA on unsupported platforms, a customer information system on borrowed time, and no functional automated meter network.
Reorganization addresses structure, not substance. It creates the appearance of progress. Ratepayers see a new name and hope for change. Reorganization changes nothing about the physical system.
In March 2026, fluoridation equipment failures were confirmed publicly, leading to a lapse in water treatment compliance[7]. Reporting also identified a $4 million operations monitoring and analysis system upgrade — a fraction of what would be needed — as one of several infrastructure projects under debate[7] — not fully funded, not fully committed[7]. If a utility cannot maintain basic treatment equipment, it is not running modern SCADA.
How a Utility Gets Here
The pattern is familiar to any aging water utility. Each budget cycle defers the problem to the next board, the next reorganization.
It starts with deferred maintenance. Tight budgets and unpopular rate increases make pipe replacement look optional, so the utility extends asset life instead. SCADA stays on Windows 2003 because the HMI still works and the operators know the interface. The cost of deferred maintenance never appears on ratepayer bills — it accumulates as invisible risk.
Eventually the first visible failures arrive. Pipe breaks increase and water main emergencies become routine, forcing the utility into emergency repairs that cost more than planned replacement. Emergency spending crowds out planned work, and the budget stretches thinner. A reactive repair fixes today's break but does nothing for the three that will happen tomorrow.
When infrastructure is under stress, governance should tighten. Instead, the opposite tends to happen. Board members become political appointees. Procurement shortcuts get justified as emergency measures. Internal controls weaken because the utility is focused on keeping water flowing, not on paperwork. The utility loses revenue at both ends — from water that leaks out of the system and from governance that lets money leak out through poor controls.
The technology gap widens while all of this is happening. Modern utilities deploy automated meters for real-time leak detection. This utility was still debating a $4 million monitoring upgrade. Modern utilities replace SCADA on a ten- to fifteen-year cycle. This utility's SCADA was running on platforms Microsoft stopped supporting in 2015. A utility that cannot measure its network cannot manage it.
When the problems become undeniable, the standard response is reorganization. A new board, a new name. But the underlying infrastructure has not changed — the SAP system remains on borrowed time, the meter gap keeps widening, and the SCADA network is still too sparse to provide useful telemetry.
What Other Utilities Should Learn From This
The Birmingham case is extreme, but the pattern is replicable. Any utility with aging infrastructure, limited capital, and political pressure to keep rates low is on the same trajectory.
A few observations emerge from the public record.
Non-revenue water above 20 percent is a warning. Above 30 percent is a crisis. Above 40 percent is a structural collapse. Every utility should treat non-revenue water as its most important operational metric. If you do not know your non-revenue water number, you do not know your utility.
SCADA running on unsupported operating systems is not a legacy problem — it is an active risk. Utilities should plan SCADA replacement on a ten- to fifteen-year cycle, not wait until the platform is two decades past its end of life.
Automated meter infrastructure is the only tool that actually reduces non-revenue water at scale. Without it, leak reduction is guesswork. Manual meter reading, visual inspections, and customer complaints are all reactive. Utilities that defer AMI are deferring the only thing that works.
Governance determines infrastructure. The audit made that clear — and the consequences followed predictably.
Renaming a utility does not fix its pipes. Reorganization addresses political accountability, not physical infrastructure.
And the trajectory is breakable, but only with external capital. Federal grants through the Bipartisan Infrastructure Law are the most promising path, but they require matching funds, demonstrated project readiness, and clean audit findings. By the time a utility realizes it needs federal money, it may be too messy to qualify.
The Bottom Line
Birmingham Water Works did not ignore its control systems. It started modernizing them. The AVEVA HMI migration was a legitimate first step. But the governance failures documented in the state audit, the equipment losses tied to missing inventory controls, the billing system countdown, and the capital budget cuts all worked against any single technical fix. A modernized HMI layer does not solve a problem that spans governance, finance, and physical infrastructure.
The 53 percent non-revenue water figure is not just about old pipes. It is about a utility that could not fund the monitoring systems needed to know which pipes were failing, could not track its own equipment, and could not bill for half its output because the systems that should have prevented all of this were either obsolete, underfunded, or both.
The Foxboro-to-AVEVA migration was a good start. It was also insufficient to address the scale of the problem.
Non-revenue water at 53 percent is not a problem that gets fixed with current reforms. It is a trajectory that gets managed, and even that requires funding the utility simply does not have.
The question for every other aging utility is not whether this pattern will repeat. It is whether they will fund the monitoring systems they need before the cost of inaction exceeds the cost of action.
References
- AVEVA Presentation: Birmingham Water Works Board's Journey to OT-IT-ET Convergence, AVEVA World San Francisco 2022. Session UC22NA-02WW70. Presenter: Dean Ford, Luminary Automation, Cybersecurity and Engineering. aveva.com
- Birmingham Watch: "40% of Water Lost to Leaks, New Birmingham Water Works Board Learns," May 20, 2025. birminghamwatch.org
- Birmingham Watch: "Capital Cuts Loom as Water Works Struggles to Balance 2026 Budget," October 15, 2025. birminghamwatch.org
- Bluefield Research: "Alabama's Largest Water Utility Reckons With Decades-Long Rise in Leakage." bluefieldresearch.com (subscription access)
- Alabama State Audit of the former Birmingham Water Works Board, December 2025. Audit period: May 1, 2023 through May 31, 2025. Available through the Alabama Legislative Services Agency.
- Birmingham Free Press: "State Audit Caps Years of Mismanagement at Birmingham Water Works," December 6, 2025. birminghamfreepress.com
- WBHM 90.3: "Former Board Pushes Back as CAW Blames Past for Fluoridation Lapse," March 27, 2026. wbhm.org
- Kurrant: "Birmingham Water Works to Advance Automated Meter System Implementation." kurrant.com
- al.com: "Birmingham Water Works Repeats History With Billing Software," September 2022. al.com
- Birmingham Water Works Board Strategic Plan and Financial Documents. bwwb.org
- ABC 33/40 (WVTM): "New Report: More Than Half of Birmingham's Water Never Reaches Customers." abc3340.com
All information in this article is drawn from public records and published reporting. No scanning, probing, or unauthorized access was performed. No specific control system assets are identified. The views expressed are the author's alone and do not represent the positions, strategies, or opinions of any government agency, department, or employer.